M-C031324-04 Schedule for Reliability-Must Run and Must-Run Alternative Processes Associated With the Notices of Suspension of Operations (NSOs) for BRAUNIG_VHB1, BRAUNIG_VHB2, and BRAUNIG_VHB3


NOTICE DATE: July 12, 2024

NOTICE TYPE: M-C031324-04 General

SHORT DESCRIPTION: Schedule for Reliability-Must Run and Must-Run Alternative Processes Associated With the Notices of Suspension of Operations (NSOs) for BRAUNIG_VHB1, BRAUNIG_VHB2, and BRAUNIG_VHB3

INTENDED AUDIENCE: All Market Participants

DAYS AFFECTED: July 25, 2024 and thereafter 

LONG DESCRIPTION:  Previously, ERCOT provided a Market Notice regarding the NSOs submitted by CPS Energy for the Generation Resources: BRAUNIG_VHB1, BRAUNIG_VHB2, and BRAUNIG_VHB3 (hereinafter, the Braunig Resources).  The NSOs indicate that, as of March 31, 2025, the Generation Resources will indefinitely suspend operations. 

ERCOT also issued a Market Notice regarding the reliability analysis conducted under ERCOT Protocols Section 3.14.1.2, ERCOT Evaluation Process, that showed these Generation Resources are needed to support ERCOT System reliability.   

Thereafter, the Public Utility Commission of Texas (PUCT) issued an Order granting ERCOT a limited good cause exception to permit variance from the deadlines in the ERCOT Protocols for the Reliability Must-Run (RMR) and Must-Run Alternative (MRA) processes associated with the proposed suspension of the Braunig Resources, including the deadlines in ERCOT Protocols § 3.14.1.2, ERCOT Evaluation Process.  

Consistent with that Order, on July 9, 2024, ERCOT filed with the PUCT an update regarding the timeline for potentially entering into one or more agreements for RMR or MRA service as a result of the planned retirement of the Braunig Resources.

 Below please find the schedule included in that filing.

Procurement Timeline[1]

CPS NSO Part III and budget due and MRA RFP Release Date 

Thursday, July 25, 2024 

CPS and ERCOT RMR Negotiation begins

Friday, July 26, 2024

Questions on MRA RFP Due from QSEs 

Monday, Aug. 5 (3:00 PM CPT) 

Questions Answered by ERCOT 

Monday, Aug. 12 

ERCOT Workshop on the MRA RFP

Thursday, Aug. 15 (afternoon)[2]

ERCOT Notice of Amendments to MRA RFP and Other Related Documents 

Wednesday, Aug. 21

QSE MRA Proposals Due 

Monday, Sep. 9 (3:00 PM CPT) 

QSE Presentations and Answers (if requested by ERCOT)  

Tuesday, Sep. 10 through Monday, Sep. 23

MRA Contract(s) Negotiation

Tuesday, Sep. 10 through Tuesday, Sep. 24

Consideration and Possible Action at ERCOT Board Reliability & Markets (R&M) Committee Meeting

Wednesday, Oct. 9, 2024

Consideration and Possible Action at ERCOT Board Meeting

Thursday, Oct. 10, 2024

Contract execution

As soon as feasible after Board approval[3]

Market Notice

Within 24 hours of signing agreement[4]



[1]  All deadlines are at 5:00 PM Central Prevailing Time (CPT), unless otherwise specified.  ERCOT Board and R&M Committee dates are not deadlines.  

[2]  The PUCT has an open meeting scheduled for the morning of Thursday, Aug. 15.

[3]  ERCOT Protocols § 3.14.1.3(2).

[4]  ERCOT Protocols § 3.14.1.2(8).

CONTACT: If you have any questions, please contact your ERCOT Account Manager. You may also call the general ERCOT Client Services phone number at (512) 248-3900 or contact ERCOT Client Services via email at ClientServices@ercot.com.