MIS LOG IN

NOGRR081

Summary

Title Synchronization with NPRR374, Modification of SCR Process and Urgency Requirements
Next Group
Next Step
Status Approved on 02/02/2012
Effective Dates
03/01/2012

Action

Date Gov Body Action Taken Next steps
02/02/2012 TAC Approved
01/12/2012 ROS Recommended for Approval TAC Consideration
11/14/2011 OWG Recommended for Approval ROS Consideration
10/19/2011 OWG Recommended for Approval OWG IA Review

Voting Record

Date Gov Body Motion Result
02/02/2012 TAC To approve NOGRR081 as recommended by ROS in the 1/12/12 ROS Report Passed
01/12/2012 ROS To recommend approval of NOGRR081 as recommended by OWG in the 11/14/11 OWG Report Passed
11/14/2011 OWG To endorse and forward the 10/19/11 OWG Report and Impact Analysis for NOGRR081 to ROS
10/19/2011 OWG Consensus to recommend approval of NOGRR081 as submitted

Background

Status: Approved
Date Posted: Oct 4, 2011
Sponsor: ERCOT
Urgent: No
Sections: 1.3.5
Description: This Nodal Operating Guide Revision Request (NOGRR) aligns the Nodal Operating Guides with changes proposed by Nodal Protocol Revision Request (NPRR) 374, which modified the requirements for Urgency.
Reason: Alignment with the Nodal Protocols by removing the rapid implementation requirement in the definition of Urgency.

Key Documents