Summary

Title Synchronization with NPRR258 and Alignment of Primary Frequency Response Test Procedures
Next Group
Next Step
Status Approved on 11/10/2011
Effective Dates
01/01/2012

Action

Date Gov Body Action Taken Next steps
12/01/2011 TAC Approved
11/10/2011 ROS Approved ROS Language Consideration

Voting Record

Date Gov Body Motion Result
12/01/2011 TAC To approve NOGRR082 as recommended by ROS in the 11/10/11 ROS Report and the Impact Analysis for NOGRR082 Passed
11/10/2011 ROS To grant NOGRR082 Urgent status Passed

Background

Status: Approved
Date Posted: Oct 7, 2011
Sponsor: ERCOT
Urgent: Yes
Sections: 8C
Description: This Nodal Operating Guide Revision Request (NOGRR) synchronizes the Nodal Operating Guides with Nodal Protocol Revision Request (NPRR) 258, Synchronization with PRR824 and PRR833 and Additional Clarifications, and revises the frequency response test procedure to be applicable to Intermittent Renewable Resources (IRRs).
Reason: Upon implementation of NPRR258, Protocol Section 8.1.1.4.1, Regulation Service and Generation Resource/Controllable Load Resource Energy Deployment Performance, ERCOT will use High Sustained Limit (HSL) for calculating Estimated Primary Frequency Response (EPFR) which is a component of Generation Resource Energy Deployment Performance (GREDP) calculation. This NOGRR will align the EPFR requirement with how the test shall be conducted for IRRs since IRRs can have significant difference between installed capacity and HSL.