NOGRR180
Summary
Title |
Exemption of Governor Dead-Band and Droop Setting Requirements for Steam Turbines of Combined Cycle Generation Resources |
Next Group |
|
Next Step |
|
Status |
Approved on 09/26/2018 |
Effective Dates |
|
Voting Record
Date |
Gov Body |
Motion |
Result |
09/26/2018
|
TAC |
To approve NOGRR180 as recommended by ROS in the 9/6/18 ROS Report. |
Passed |
09/06/2018
|
ROS |
To endorse and forward to TAC the 8/9/18 ROS Report and Impact Analysis for NOGRR180. |
Passed |
08/09/2018
|
ROS |
To recommend approval of NOGRR0180 as submitted. |
Passed |
07/12/2018
|
ROS |
To table NOGRR180 and refer the issue to the Performance, Disturbance, Compliance Working Group (PDCWG). |
Passed |
Background
Status: |
Approved |
Date Posted: |
Jun 26, 2018
|
Sponsor: |
ERCOT |
Urgent: |
No |
Sections: |
2.2.7 |
Description: |
This Nodal Operating Guide Revision Request (NOGGR) removes Governor Dead-Band and Governor droop settings requirements for steam turbines of Combined Cycle Generation Resources. |
Reason: |
Addresses current operational issues |