MIS LOG IN

NOGRR180

Summary

Title Exemption of Governor Dead-Band and Droop Setting Requirements for Steam Turbines of Combined Cycle Generation Resources
Next Group
Next Step
Status Approved on 09/26/2018
Effective Dates
10/01/2018

Action

Date Gov Body Action Taken Next Steps
09/26/2018 TAC Approved
09/06/2018 ROS Recommended for Approval Revision Request Consideration
08/09/2018 ROS Recommended for Approval Impact Analysis Consideration
07/12/2018 ROS Deferred/Tabled Language Consideration

Voting Record

Date Gov Body Motion Result
09/26/2018 TAC To approve NOGRR180 as recommended by ROS in the 9/6/18 ROS Report. Passed
09/06/2018 ROS To endorse and forward to TAC the 8/9/18 ROS Report and Impact Analysis for NOGRR180. Passed
08/09/2018 ROS To recommend approval of NOGRR0180 as submitted. Passed
07/12/2018 ROS To table NOGRR180 and refer the issue to the Performance, Disturbance, Compliance Working Group (PDCWG). Passed

Background

Status: Approved
Date Posted: Jun 26, 2018
Sponsor: ERCOT
Urgent: No
Sections: 2.2.7
Description: This Nodal Operating Guide Revision Request (NOGGR) removes Governor Dead-Band and Governor droop settings requirements for steam turbines of Combined Cycle Generation Resources.
Reason: Addresses current operational issues