NOGRR189
Summary
Title
Align Disturbance Monitoring Requirements Deadline with NERC Reliability Standard PRC-002-2
Next Group
Next Step
Status
Approved on 05/22/2019
Effective Dates
Voting Record
Date
Gov Body
Motion
Result
05/22/2019
TAC
to approve NOGRR189 as recommended by ROS in the 5/2/19 ROS Report as revised by TAC
Passed
05/02/2019
ROS
to endorse and forward to TAC the 4/4/19 ROS Report and the Impact Analysis for NOGRR189
Passed
04/04/2019
ROS
to recommend approval of NOGRR189 as submitted
Passed
Background
Status:
Approved
Date Posted:
Mar 20, 2019
Sponsor:
System Protection Working Group
Urgent:
No
Sections:
6.1.2.2, 6.1.3.2
Description:
This Nodal Operating Guide Revision Request (NOGRR) aligns the Nodal Operating Guides with North American Electric Reliability Corporation (NERC) Reliability Standard PRC-002-2 – Disturbance Monitoring and Reporting Requirements.
Reason:
Regulatory requirements