MIS LOG IN

NOGRR189

Summary

Title Align Disturbance Monitoring Requirements Deadline with NERC Reliability Standard PRC-002-2
Next Group
Next Step
Status Approved on 05/22/2019
Effective Dates
06/01/2019

Action

Date Gov Body Action Taken Next Steps
05/22/2019 TAC Approved
05/02/2019 ROS Recommended for Approval Revision Request Consideration
04/04/2019 ROS Recommended for Approval Impact Analysis Consideration

Voting Record

Date Gov Body Motion Result
05/22/2019 TAC to approve NOGRR189 as recommended by ROS in the 5/2/19 ROS Report as revised by TAC Passed
05/02/2019 ROS to endorse and forward to TAC the 4/4/19 ROS Report and the Impact Analysis for NOGRR189 Passed
04/04/2019 ROS to recommend approval of NOGRR189 as submitted Passed

Background

Status: Approved
Date Posted: Mar 20, 2019
Sponsor: System Protection Working Group
Urgent: No
Sections: 6.1.2.2, 6.1.3.2
Description: This Nodal Operating Guide Revision Request (NOGRR) aligns the Nodal Operating Guides with North American Electric Reliability Corporation (NERC) Reliability Standard PRC-002-2 – Disturbance Monitoring and Reporting Requirements.
Reason: Regulatory requirements

Key Documents