Title Related to NPRR1093, Load Resource Participation in Non-Spinning Reserve
Next Group
Next Step
Status Approved on 10/28/2021

Action

Date Gov Body Action Taken Next Steps
10/28/2021 PUCT Approved
10/22/2021 BOARD Recommended for Approval PUCT for consideration
09/29/2021 TAC Recommended for Approval Board for consideration
09/21/2021 ROS Recommended for Approval TAC for consideration

Voting Record

Date Gov Body Motion Result
10/28/2021 PUCT To approve NOGRR232 and accompanying ERCOT Market Impact Statement as presented in Project No. 52307, Review of Rules Adopted by the Independent Organization in Calendar Year 2021 Passed
10/22/2021 BOARD To recommend approval of NOGRR232 as recommended by TAC in the 9/29/21 TAC Report Passed
09/29/2021 TAC To recommend approval of NOGRR232 as recommended by ROS in the 9/21/21 ROS Report Passed
09/21/2021 ROS To grant NOGRR232 Urgent status; to recommend approval of NOGRR232 as submitted; and to forward to TAC NOGRR232 and the Impact Analysis Passed

Background

Status: Approved
Date Posted: Sep 1, 2021
Sponsor: ERCOT
Urgent: Yes
Sections: 2.3 and 2.3.2.1
Description: This Nodal Operating Guide Revision Request (NOGRR) aligns the Nodal Operating Guide with revisions from NPRR1093 to allow Load Resources that are not Controllable Load Resources to provide Non-Spinning Reserve (Non-Spin) Ancillary Service.
Reason: Addresses current operational issues / Meets Strategic goals (tied to the ERCOT Strategic Plan or directed by the ERCOT Board) / Market efficiencies or enhancements