NPRR1032

Summary

Title Consideration of Physical Limits of DC Ties in RUC Optimization and Settlements
Next Group
Next Step
Status Approved on 12/08/2020

Action

Date Gov Body Action Taken Next Steps
12/08/2020 BOARD Approved
10/28/2020 TAC Recommended for Approval Revision Request Consideration
10/15/2020 PRS Recommended for Approval Revision Request Consideration
09/10/2020 PRS Recommended for Approval Impact Analysis Consideration
08/13/2020 PRS Deferred/Tabled Language Consideration

Voting Record

Date Gov Body Motion Result
12/08/2020 BOARD to approve NPRR1032 as recommended by TAC in the 10/28/20 TAC Report Passed
10/28/2020 TAC to recommend approval of NPRR1032 as recommended by PRS in the 10/15/20 PRS Report Passed
10/15/2020 PRS to endorse and forward to TAC the 9/10/20 PRS Report and Impact Analysis for NPRR1032 with a recommended priority of 2021 and rank of 3260 Passed
09/10/2020 PRS to recommend approval of NPRR1032 as submitted Passed
08/13/2020 PRS to table NPRR1032 Passed

Background

Status: Approved
Date Posted: Jul 17, 2020
Sponsor: ERCOT
Urgent: No
Sections: 5.5.2, 5.7.4.1.1, 6.6.3.4
Description: This Nodal Protocol Revision Request (NPRR) will limit the Direct Current Tie (DC Tie) schedules used in Reliability Unit Commitment (RUC) optimization and RUC Settlements to the physical rating of the DC Tie.
Reason: Addresses current operational issues.