NPRR257
Summary
Title | Synchronization with Nodal Operating Guide Section 9, Monitoring Programs and Changes to Posting Requirements of Documents Considered CEII (formerly "Synchronization with Nodal Operating Guide Section 9, Monitoring Programs") |
---|---|
Next Group | |
Next Step | |
Status | Approved on 11/16/2010 |
Effective Dates |
01/03/2011
Sections 6.5.7.3(partial) and 8.2(partial) 12/01/2010
Sections 6.5.9.6, 8.1(partial), 8.2(partial), and 8.3(partial) |
Action
Date | Gov Body | Action Taken | Next Steps |
---|---|---|---|
11/16/2010 | BOARD | Approved | |
11/04/2010 | TAC | Recommended for Approval | ERCOT Board Consideration |
10/21/2010 | PRS | Recommended for Approval | TAC Consideration |
09/23/2010 | PRS | Recommended for Approval | PRS IA Review |
08/19/2010 | PRS | Referred | PRS Review |
Voting Record
Date | Gov Body | Motion | Result |
---|---|---|---|
11/16/2010 | BOARD | To approve NPRR257 as recommended by TAC in the 11/4/10 TAC Report | Passed |
11/04/2010 | TAC | To recommend approval of NPRR257 as amended by the 11/3/10 ERCOT comments and to recommend a priority of High/Medium to the grey-boxed language | Passed |
10/21/2010 | PRS | To endorse and forward the 9/23/10 PRS Report as amended by the 10/19/10 ERCOT comments and revised Impact Analysis for NPRR257 to TAC and to recommend a priority of High/Medium for the grey-boxed language | Passed |
09/23/2010 | PRS | To recommend approval of NPRR257 as amended by the 9/16/10 ERCOT comments. | Passed |
08/19/2010 | PRS | To refer NPRR257 to the Nodal Advisory Task Force (NATF) | Passed |
Background
Status: | Approved |
---|---|
Date Posted: | Jul 22, 2010 |
Sponsor: | ERCOT |
Urgent: | No |
Sections: | 6.5.7.3, 6.5.9.6, 8, 8.1, 8.2, 8.3 |
Description: | This Nodal Protocol Revision Request (NPRR) grey-boxes multiple sections of the Nodal Protocols to align with Nodal Operating Guide Section 9, Monitoring Programs. This NPRR also changes the posting requirement for certain Black Start documents which meet the definition of Critical Energy Infrastructure Information (CEII) and removes the requirement for posting Black Start procedures for Resource Entities that have Black Start Agreements with ERCOT since 8.1 is related to performance monitoring. |
Reason: | Aligns the Nodal Protocols with Nodal Operating Guide Section 9and changes the posting requirement of Black Start documents which meet the definition of CEII. |