NPRR738
Summary
Title
ERS Performance Calculations During TDSP Outages
Next Group
Next Step
Status
Approved on 08/09/2016
Effective Dates
Voting Record
Date
Gov Body
Motion
Result
08/09/2016
BOARD
To approve NPRR738 as recommended by TAC in the 7/28/16 TAC Report.
Passed
07/28/2016
TAC
To recommend approval of NPRR738 as recommended by PRS in the 6/16/16 PRS Report.
Passed
06/16/2016
PRS
To endorse and forward to TAC the 5/12/16 PRS Report as amended by the 5/31/16 MP2 Energy comments and the Impact Analysis for NPRR738.
Passed
05/12/2016
PRS
To recommend approval of NPRR738 as amended by the 5/5/16 WMS comments
Passed
11/12/2015
PRS
To table NPRR738 and refer the issue to WMS.
Passed
Background
Status:
Approved
Date Posted:
Oct 21, 2015
Sponsor:
MP2 Energy, LLC.
Urgent:
No
Sections:
8.1.3.1.4
Description:
This Nodal Protocol Revision Request (NPRR) excludes intervals from performance calculations for which an Emergency Response Service (ERS) Generator is unable to meet its obligations due to Transmission and/or Distribution Service Provider (TDSP) Outages.
Reason:
Market efficiencies and enhancements.