NPRR747

Summary

Title Revision of Voltage Control Requirements
Next Group
Next Step
Status Approved on 10/11/2016
Effective Dates
01/01/2017

Action

Date Gov Body Action Taken Next Steps
10/11/2016 BOARD Approved
07/28/2016 TAC Recommended for Approval Board for consideration
07/14/2016 PRS Recommended for Approval TAC for consideration
06/16/2016 PRS Recommended for Approval PRS for Impact Analysis review
12/10/2015 PRS Deferred/Tabled Language Consideration

Voting Record

Date Gov Body Motion Result
10/11/2016 BOARD To approve NPRR747 as recommended by TAC in the 7/28/16 TAC Report with an ERCOT Board action effective date of 8/9/16 Passed
07/28/2016 TAC To recommend approval of NPRR747 as recommended by PRS in the 7/14/16 PRS Report Passed
07/14/2016 PRS To endorse and forward to TAC the 6/16/16 PRS Report and Impact Analysis for NPRR747 Passed
06/16/2016 PRS To recommend approval of NPRR747 as amended by the 4/21/16 ERCOT comments Passed
12/10/2015 PRS To table NPRR747 and refer the issue to WMS and ROS. Passed

Background

Status: Approved
Date Posted: Nov 25, 2015
Sponsor: ERCOT
Urgent: No
Sections: 2.1, 3.15, 3.15.3, 6.5.7.7
Description: This Nodal Protocol Revision Request (NPRR) proposes new definitions related to Voltage Profiles, defines various entities’ responsibilities related to Voltage Support, and also clarifies that the interconnecting Transmission Service Provider (TSP) (or its designated agent) may modify a Generation Resource’s Voltage Set Point). This NPRR addresses issues raised at the April 8, 2015 Voltage Workshop.
Reason: Addresses current operational issues.