NPRR858
Summary
Title |
Provide Complete Current Operating Plan (COP) Data |
Next Group |
|
Next Step |
|
Status |
Approved on 04/10/2018 |
Effective Dates |
|
Voting Record
Date |
Gov Body |
Motion |
Result |
04/10/2018
|
BOARD |
To approve NPRR858 as recommended by TAC in the 3/22/18 TAC Report. |
Passed |
03/22/2018
|
TAC |
To recommend approval of NPRR858 as recommended by PRS in the 3/8/18 PRS Report. |
Passed |
03/08/2018
|
PRS |
To endorse and forward to TAC the 2/8/18 PRS Report and the Impact Analysis for NPRR858 with a recommended priority of 2018 and a rank of 2170. |
Passed |
02/08/2018
|
PRS |
To recommend approval of NPRR858 as submitted. |
Passed |
01/18/2018
|
PRS |
To table NPRR858 for one month and refer the issue to WMS. |
Passed |
Background
Status: |
Approved |
Date Posted: |
Dec 4, 2017
|
Sponsor: |
Citigroup Energy Inc. |
Urgent: |
No |
Sections: |
1.3.3 |
Description: |
This Nodal Protocol Revision Request (NPRR) will publish all Current Operating Plan (COP) data after confidentiality has expired. |
Reason: |
Meets Strategic goals (tied to the ERCOT Strategic Plan or directed by the ERCOT Board) |