NPRR866
Summary
Title | Mapping Registered Distributed Generation and Load Resources to Transmission Loads in the Network Operations Model |
---|---|
Next Group | |
Next Step | |
Status | Approved on 08/07/2018 |
Effective Dates |
04/05/2019
|
Action
Date | Gov Body | Action Taken | Next Steps |
---|---|---|---|
08/07/2018 | BOARD | Approved | |
07/26/2018 | TAC | Recommended for Approval | Revision Request Consideration |
07/19/2018 | PRS | Recommended for Approval | Revision Request Consideration |
06/14/2018 | PRS | Recommended for Approval | Impact Analysis Consideration |
03/08/2018 | PRS | Deferred/Tabled | Language Consideration |
Voting Record
Date | Gov Body | Motion | Result |
---|---|---|---|
08/07/2018 | BOARD | To approve NPRR866 as recommended by TAC in the 7/26/18 TAC Report. | Passed |
07/26/2018 | TAC | To recommend approval of NPRR866 as recommended by PRS in the 7/19/18 PRS Report. | Passed |
07/19/2018 | PRS | To endorse and forward to TAC the 6/14/18 PRS Report and Impact Analysis for NPRR866 with a recommended priority of 2018 and a rank of 2270. | Passed |
06/14/2018 | PRS | To recommend approval of NPRR866 as amended by the 5/16/18 Oncor comments as revised by PRS. | Passed |
03/08/2018 | PRS | To table NPRR866 and to refer the issue to ROS and WMS. | Passed |
Background
Status: | Approved |
---|---|
Date Posted: | Feb 14, 2018 |
Sponsor: | ERCOT |
Urgent: | No |
Sections: | 3.10.7.2 |
Description: | This Nodal Protocol Revision Request (NPRR) accomplishes two objectives related to mapping registered Distributed Generation (DG) and Load Resources to transmission Loads in the Network Operations Model. Specifically, this NPRR expands paragraph (2) of Section 3.10.7.2 to codify the existing process for mapping a Load Resource or an Aggregate Load Resource (ALR) to its appropriate Load point in the Network Operations Model; and outlines in a new paragraph (3) of Section 3.10.7.2 the practice for mapping a registered DG facility to its appropriate Load point in the Network Operations Model. These changes would affect all existing and future DG facilities that have registered or will register with ERCOT pursuant to paragraph (5) of Section 16.5, Registration of a Resource Entity. DG registration is required for any DG facility with a capacity rating above the registration threshold, currently set at 1 MW, and which injects energy to the distribution grid. Registration with ERCOT is optional for smaller DG facilities. |
Reason: | Addresses current operational issues; Meets Strategic goals, Market efficiencies or enhancements |
Key Documents
Feb 14, 2018 - doc - 57 KB
Mar 2, 2018 - doc - 41.5 KB
Mar 12, 2018 - doc - 112.5 KB
Apr 5, 2018 - doc - 40.5 KB
Apr 6, 2018 - doc - 41 KB
May 16, 2018 - doc - 51 KB
Jun 12, 2018 - doc - 41.5 KB
Jun 14, 2018 - doc - 102.5 KB
Jul 19, 2018 - doc - 103.5 KB
Jul 26, 2018 - doc - 105.5 KB
Aug 8, 2018 - doc - 106 KB