NPRR880

Summary

Title Publish Real-Time Market Shift Factors for Private Use Network Settlement Points
Next Group
Next Step
Status Approved on 10/09/2018
Effective Dates
04/05/2019

Action

Date Gov Body Action Taken Next Steps
10/09/2018 BOARD Approved
09/26/2018 TAC Recommended for Approval Board for consideration
09/13/2018 PRS Recommended for Approval TAC for consideration
08/16/2018 PRS Recommended for Approval PRS for Impact Analysis review
07/19/2018 PRS Deferred/Tabled PRS for consideration

Voting Record

Date Gov Body Motion Result
10/09/2018 BOARD To approve NPRR880 as recommended by TAC in the 9/26/18 TAC Report Passed
09/26/2018 TAC To recommend approval of NPRR880 as recommended by PRS in the 9/13/18 PRS Report Passed
09/13/2018 PRS To endorse and forward to TAC the 8/16/18 PRS Report and Impact Analysis for NPRR880 with a recommended priority of 2018 and rank of 2300 Passed
08/16/2018 PRS To recommend approval of NPRR880 as submitted Passed
07/19/2018 PRS To table NPRR880 and refer the issue to WMS Passed

Background

Status: Approved
Date Posted: Jun 19, 2018
Sponsor: DC Energy
Urgent: No
Sections: 6.5.7.1.13
Description: This Nodal Protocol Revision Request (NPRR) requires ERCOT to publish Shift Factors for Private Use Network Settlement Points for the Real-Time Market (RTM).
Reason: Meets Strategic goals

Key Documents

Related Content