NPRR882
Summary
Title
Related to PGRR067, Procedures for Wind and Solar Equipment Change
Next Group
Next Step
Status
Approved on 12/11/2018
Effective Dates
Voting Record
Date
Gov Body
Motion
Result
12/11/2018
BOARD
To approve NPRR882 as recommended by TAC in the 11/29/18 TAC Report.
Passed
11/29/2018
TAC
To recommend approval of NPRR882 as recommended by PRS in the 11/15/18 PRS Report.
Passed
11/15/2018
PRS
To endorse and forward to TAC the 10/18/18 PRS Report and Revised Impact Analysis for NPRR882.
Passed
10/18/2018
PRS
To recommend approval of NPRR882 as amended by the 9/13/18 ERCOT comments.
Passed
07/19/2018
PRS
To table NPRR882 and refer the issue to ROS.
Passed
Background
Status:
Approved
Date Posted:
Jun 26, 2018
Sponsor:
ERCOT
Urgent:
No
Sections:
2.1 and ERCOT Fee Schedule
Description:
This Nodal Protocol Revision Request (NPRR) updates the definition of Initial Synchronization and Interconnecting Entity to include certain types of facility equipment changes and clarifies Generation Interconnection or Change Request (GINR)-related fee language.
Reason:
Addresses current operational issues
ERCOT-Lockup-white