MIS LOG IN

NPRR922

Summary

Title Modifications to DC Tie Import Forecast Method
Next Group
Next Step
Status Approved on 04/09/2019
Effective Dates
05/01/2019

Action

Date Gov Body Action Taken Next Steps
04/09/2019 BOARD Approved
03/27/2019 TAC Recommended for Approval Board for consideration
03/14/2019 PRS Recommended for Approval TAC for consideration
02/14/2019 PRS Recommended for Approval PRS for Impact Analysis review

Voting Record

Date Gov Body Motion Result
04/09/2019 BOARD to approve NPRR922 as recommended by TAC in the 3/27/19 TAC Report Passed
03/27/2019 TAC To recommend approval of NPRR922 as recommended by PRS in the 3/14/19 PRS Report Passed
03/14/2019 PRS To endorse and forward to TAC the 2/14/19 PRS Report and Impact Analysis for NPRR922 Passed
02/14/2019 PRS To recommend approval of NPRR922 as revised by PRS Passed

Background

Status: Approved
Date Posted: Jan 30, 2019
Sponsor: ERCOT
Urgent: No
Sections: 3.2.6.2.2
Description: This Nodal Protocol Revision Request (NPRR) aligns the Direct Current Tie (DC Tie) import forecast with forecasts of other Resources in the Report on Capacity, Demand and Reserves in the ERCOT Region (“CDR”) that are deployed during Energy Emergency Alert (EEA) events, such as Emergency Response Service (ERS). This NPRR also addresses a reporting gap in the CDR by specifying an approach for forecasting expected capacity imports for planned DC Tie projects.
Reason: