PGRR014

    Summary

    Title: Synchronization with NPRR374, Modification of SCR Process and Urgency Requirements
    Next Group:
    Next Step:
    Status: Approved on 04/17/2012
    Effective Date: 05/01/2012

    Action

    Date Gov Body Action Taken Next Steps
    04/17/2012 Board of Directors Approved
    02/02/2012 TAC Recommended for Approval ERCOT Board Consideration
    01/01/2012 ROS Recommended for Approval TAC Consideration
    11/28/2011 PLWG Recommended for Approval ROS Consideration
    10/28/2011 PLWG Recommended for Approval PLWG IA Review

    Voting Record

    Date Gov Body Motion Result
    04/17/2012 Board of Directors To approve PGRR014 as recommended by TAC in the 2/2/12 TAC Report Passed
    02/02/2012 TAC To recommend approval of PGRR014 as recommended by ROS in the 1/12/12 ROS Report Passed
    01/01/2012 ROS To recommend approval of PGRR014 as recommended by PLWG in the 11/28/11 PLWG Report Passed
    11/28/2011 PLWG Consensus to endorse and forward the 10/28/11 PLWG Report and Impact Analysis for PGRR014 to ROS
    10/28/2011 PLWG Consensus to recommend approval of PGRR014 as submitted

    Vote tallies here reflect individual votes, not the weight of the votes by market segment. Affirmative votes are not recorded in these vote tallies. For additional details on the voting record, please consult the Recommendation or Action Report, or the official vote tally if available, as posted in the key documents.

    Background

    Status: Approved
    Date Posted: 10/06/2011
    Sponsor: ERCOT
    Urgent: No
    Sections: 1.5
    Description: This Planning Guide Revision Request (PGRR) aligns the Planning Guide with changes proposed by Nodal Protocol Revision Request (NPRR) 374, which modified the requirements for Urgency.
    Reason: Alignment with the Nodal Protocols by removing the rapid implementation requirement in the definition of Urgency.

    Key Documents