MIS LOG IN

PGRR023

Summary

Title Contingency Filing Requirements
Next Group
Next Step
Status Approved on 03/19/2013
Effective Dates
04/01/2013

Action

Date Gov Body Action Taken Next Steps
03/19/2013 BOARD Approved
02/07/2013 TAC Recommended for Approval ERCOT Board Consideration
01/10/2013 ROS Recommended for Approval TAC Consideration
12/04/2012 PLWG Recommended for Approval ROS Consideration
10/25/2012 PLWG Recommended for Approval PLWG IA Review

Voting Record

Date Gov Body Motion Result
03/19/2013 BOARD To approve PGRR023 as recommended by TAC in the 2/7/13 TAC Report Passed
02/07/2013 TAC To recommend approval of PGRR023 as recommended by ROS in the 1/10/13 ROS Report Passed
01/10/2013 ROS To recommend approval of PGRR023 as recommended by PLWG in the 12/4/12 PLWG Report Passed
12/04/2012 PLWG To endorse and forward the 10/25/12 PLWG Report and Impact Analysis to ROS
10/25/2012 PLWG Consensus to recommend approval of PGRR023 as revised by PLWG

Background

Status: Approved
Date Posted: Oct 10, 2012
Sponsor: PLWG
Urgent: No
Sections: 6.9
Description: This Planning Guide Revision Request (PGRR) adds a requirement for Transmission Service Providers (TSPs) to submit and annually review a list of contingencies for their portion of the ERCOT System. The language ensures that the appropriate contingencies are being submitted for ERCOT and North American Electric Reliability Corporation (NERC) planning criteria.
Reason: There are currently no requirements in the Protocols or Market Guides for TSPs to submit their contingency lists. The contingency definitions are critical for planning the ERCOT System.

Key Documents

Related Content