PGRR051

Summary

Title Alignment with NPRR792, Changing Special Protection System (SPS) to Remedial Action Scheme (RAS)
Next Group
Next Step
Status Approved on 12/13/2016
Effective Dates
04/01/2017

Action

Date Gov Body Action Taken Next Steps
12/13/2016 BOARD Approved
12/01/2016 TAC Recommended for Approval Revision Request Consideration
10/27/2016 TAC Deferred/Tabled Revision Request Consideration
10/06/2016 ROS Recommended for Approval Revision Request Consideration
09/21/2016 PLWG Recommended for Approval Revision Request Consideration
08/17/2016 PLWG Recommended for Approval Impact Analysis Consideration

Voting Record

Date Gov Body Motion Result
12/13/2016 BOARD To approve PGRR051 as recommended by TAC in the 12/1/16 TAC Report. Passed
12/01/2016 TAC To recommend approval of PGRR051 as recommended by ROS in the 10/6/16 ROS Report. Passed
10/27/2016 TAC To table PGRR051 Passed
10/06/2016 ROS To recommend approval of PGRR051 as recommended by PLWG in the 9/21/16 PLWG Report. Passed
09/21/2016 PLWG To endorse and forward to ROS the 8/17/16 PLWG Report and Impact Analysis for PGRR051 Passed
08/17/2016 PLWG To recommend approval of PGRR051 as submitted Passed

Background

Status: Approved
Date Posted: Jul 27, 2016
Sponsor: ERCOT
Urgent: No
Sections: 6.2.3, 6.4.1
Description: This Planning Guide Revision Request (PGRR) aligns the Planning Guides with North American Electric Reliability Corporation (NERC) Reliability Standard definition for Special Protection System (SPS) and for consistency uses Remedial Action Scheme (RAS) and Automatic Mitigation Plan (AMP) where applicable in place of SPS.
Reason: Regulatory Requirements

Key Documents

Related Content