Title | Addition of Proposed Generation Resources to the Planning Models |
---|---|
Next Group | |
Next Step | |
Status | Approved on 02/14/2017 |
Effective Dates |
03/01/2017
|
Action
Date | Gov Body | Action Taken | Next Steps |
---|---|---|---|
02/14/2017 | BOARD | Approved | |
01/26/2017 | TAC | Recommended for Approval | Revision Request Consideration |
01/12/2017 | ROS | Recommended for Approval | Revision Request Consideration |
12/21/2016 | PLWG | Recommended for Approval | Revision Request Consideration |
11/16/2016 | PLWG | Recommended for Approval | Impact Analysis Consideration |
10/19/2016 | PLWG | Deferred/Tabled | Language Consideration |
Voting Record
Date | Gov Body | Motion | Result |
---|---|---|---|
02/14/2017 | BOARD | To approve PGRR053 as recommended by TAC in the 1/26/17 TAC Report. | Passed |
01/26/2017 | TAC | To recommend approval of PGRR053 as recommended by ROS in the 1/12/17 ROS Report and as revised by TAC. | Passed |
01/12/2017 | ROS | To recommend approval of PGRR053 as recommended by PLWG in the 12/21/16 PLWG Report. | Passed |
12/21/2016 | PLWG | To endorse and forward to ROS the 11/16/16 PLWG Report and Impact Analysis for PGRR053. | Passed |
11/16/2016 | PLWG | To recommend approval of PGRR053 as revised by PLWG. | Passed |
10/19/2016 | PLWG | To table PGRR053. | Passed |
Background
Status: | Approved |
---|---|
Date Posted: | Sep 29, 2016 |
Sponsor: | PLWG |
Urgent: | No |
Sections: | 6.9; 8 Attachment B |
Description: | This Planning Guide Revision Request (PGRR) modifies the conditions that need to be met prior to including proposed Generation Resources in the planning models. This proposal includes limiting the initial data required for inclusion in the Steady State Working Group (SSWG) base cases to the data provided for the Full Interconnection Studies (FISs). ERCOT’s System Planning Monthly Status Reports consistently indicate a significant amount of proposed Generation Resources meeting all existing inclusion conditions (Standard Generation Interconnection Agreement (SGIA), applicable permits, notice to proceed, and financial security) with the exception of providing sufficient data required as indicated in the Resource Registration Glossary. The exclusion of the proposed Generation Resources from the Planning Models which have met all other inclusion conditions except for providing sufficient Resource Asset Registration Form (RARF) data has created a need to unnecessarily use extraordinary Dispatch conditions in the SSWG base cases. This PGRR will allow SSWG to utilize more representative generation Dispatch scenarios in their base cases. |
Reason: | Addresses current operations issues; Market efficiencies or enhancements |
Key Documents
Sep 29, 2016 - docx - 45.2 KB
Oct 21, 2016 - doc - 104.5 KB
Nov 15, 2016 - doc - 41 KB
Nov 18, 2016 - doc - 106.5 KB
Dec 12, 2016 - doc - 56.5 KB
Dec 23, 2016 - doc - 106.5 KB
Jan 13, 2017 - doc - 108.5 KB
Feb 1, 2017 - doc - 112 KB
Feb 14, 2017 - doc - 112.5 KB