Summary

Title Clarification of Reliability Performance Criteria
Next Group
Next Step
Status Approved on 06/12/2018
Effective Dates
07/01/2018

Action

Date Gov Body Action Taken Next Steps
06/12/2018 BOARD Approved
05/24/2018 TAC Recommended for Approval Revision Request Consideration
04/05/2018 ROS Recommended for Approval Revision Request Consideration
03/01/2018 ROS Recommended for Approval Impact Analysis Consideration

Voting Record

Date Gov Body Motion Result
06/12/2018 BOARD To approve PGRR060 as recommended by TAC in the 5/24/18 TAC Report. Passed
05/24/2018 TAC To recommend approval of PGRR060 as recommended by ROS in the 4/5/18 ROS Report. Passed
04/05/2018 ROS To endorse and forward to TAC the 3/1/18 ROS Report and Impact Analysis for PGRR060 Passed
03/01/2018 ROS To recommend approval of PGRR060 as revised by ROS. Passed

Background

Status: Approved
Date Posted: Feb 14, 2018
Sponsor: ERCOT
Urgent: No
Sections: 4.1.1.2
Description: This Planning Guide Revision Request (PGRR) updates the reliability performance criteria by defining unavailability of a Direct Current Tie (DC Tie) as a new contingency. The PGRR also includes clarification of the voltage level of transformers referred to in the reliability performance criteria.
Reason: Addresses current operational issues