Title | Updates to Generation Interconnection or Change Request (GINR) Process |
---|---|
Next Group | |
Next Step | |
Status | Approved on 08/07/2018 |
Effective Dates |
01/01/2019
Sections 5.2.1, 5.2.2, 5.3, 5.3.1, 5.3.2, 5.4.1, 5.4.2.1, 5.4.7, 5.4.8, 5.4.10, 5.5.4, 5.7.1, 5.7.3, 5.7.4, 5.7.5, 8A, 8B 03/26/2019
All remaining sections |
Action
Date | Gov Body | Action Taken | Next Steps |
---|---|---|---|
08/07/2018 | BOARD | Approved | |
07/26/2018 | TAC | Recommended for Approval | Revision Request Consideration |
07/12/2018 | ROS | Recommended for Approval | Revision Request Consideration |
06/07/2018 | ROS | Recommended for Approval | Impact Analysis Consideration |
04/05/2018 | ROS | Deferred/Tabled | Language Consideration |
Voting Record
Date | Gov Body | Motion | Result |
---|---|---|---|
08/07/2018 | BOARD | To approve PGRR062 as recommended by TAC in the 7/26/18 TAC Report. | Passed |
07/26/2018 | TAC | To recommend approval of PGRR062 as recommended by ROS in the 7/12/18 ROS Report as revised by TAC. | Passed |
07/12/2018 | ROS | To endorse and forward to TAC the 6/7/18 ROS Report, as amended by the 7/3/18 ERCOT comments, and the Impact Analysis for PGRR062. | Passed |
06/07/2018 | ROS | To recommend approval of PGRR062 as amended by the 5/21/18 ERCOT comments as revised by ROS. | Passed |
04/05/2018 | ROS | To table PGRR062 and refer the issue to the Planning Working Group (PLWG). | Passed |
Background
Status: | Approved |
---|---|
Date Posted: | Mar 21, 2018 |
Sponsor: | ERCOT |
Urgent: | No |
Sections: | 5.2.1, 5.2.2, 5.3, 5.3.1, 5.3.2, 5.4.1, 5.4.2.1, 5.4.7, 5.4.8, 5.4.10, 5.5.4, 5.7.1, 5.7.2, 5.7.3, 5.7.4, and 5.7.5 |
Description: | This Planning Guide Revision Request (PGRR) proposes new processes, communication, and document sharing and storage requirements to be included in the new Generation Interconnection or Change Request (GINR) application. |
Reason: | Market efficiencies or enhancements |