MIS LOG IN

PGRR066

Summary

Title Interconnection Request Cancellation and Creation of Inactive Status
Next Group
Next Step
Status Approved on 12/11/2018
Effective Dates
08/01/2019

Action

Date Gov Body Action Taken Next Steps
12/11/2018 BOARD Approved
11/29/2018 TAC Recommended for Approval Revision Request Consideration
11/08/2018 ROS Recommended for Approval Revision Request Consideration
10/11/2018 ROS Recommended for Approval Impact Analysis Consideration
07/12/2018 ROS Deferred/Tabled Language Consideration

Voting Record

Date Gov Body Motion Result
12/11/2018 BOARD to approve PGRR066 as recommended by TAC in the 11/29/18 TAC Report Passed
11/29/2018 TAC to recommend approval of PGRR066 as recommended by ROS in the 11/8/18 ROS Report Passed
11/08/2018 ROS to endorse and forward to TAC the 10/11/18 ROS Report and Impact Analysis for PGRR066 with a recommended priority of 2019 and a rank of 2580 Passed
10/11/2018 ROS to recommend approval of PGRR066 as amended by the 9/12/18 ERCOT comments as revised by ROS Passed
07/12/2018 ROS to table PGRR066 and refer the issue to the Planning Working Group (PLWG) Passed

Background

Status: Approved
Date Posted: Jun 26, 2018
Sponsor: ERCOT
Urgent: No
Sections: 5.2.1, 5.3.2, 5.4.8, 5.5.1, 5.7.1, 5.7.6 (new), and 5.7.7 (new)
Description: This Planning Guide Revision Request (PGRR) creates an Inactive Status for Generation Interconnection and Change Request (GINR) projects that will not be listed in ERCOT monthly Generation Interconnection Status report but will retain the interconnection request numbers. This PGRR also defines a process that can be used to cancel interconnection requests that have failed to meet requirements.
Reason: Market efficiencies or enhancements

Key Documents

Related Content