PGRR067
Summary
Title
Procedures for Wind and Solar Equipment Change
Next Group
Next Step
Status
Approved on 12/11/2018
Effective Dates
Voting Record
Date
Gov Body
Motion
Result
12/11/2018
BOARD
To approve PGRR67 as recommended by TAC in the 11/29/18 TAC Report.
Passed
11/29/2018
TAC
To recommend approval of PGRR067 as recommended by ROS in the 11/8/18 ROS Report.
Passed
11/08/2018
ROS
To endorse and forward to TAC the 10/11/18 ROS Report and Revised Impact Analysis for PGRR067.
Passed
10/11/2018
ROS
To recommend approval of PGRR067 as amended by the 9/13/18 ERCOT comments as revised by ROS.
Passed
09/06/2018
ROS
To table PGRR067.
Passed
08/09/2018
ROS
To table PGRR067.
Passed
07/12/2018
ROS
To table PGRR067 and refer the issue to the Planning Working Group (PLWG).
Passed
Background
Status:
Approved
Date Posted:
Jun 26, 2018
Sponsor:
ERCOT
Urgent:
No
Sections:
5.1.1, 5.2.1, 5.2.2, 5.3, 5.3.1, 5.4.1, 5.4.2, 5.4.2.1, 5.7.2, 5.7.3, and 5.9
Description:
This Planning Guide Revision Request (PGRR) describes how wind and solar facility equipment changes are treated throughout the generation interconnection process and clarifies language for Generation Interconnection or Change Request (GINR)-related fees.
Reason:
Addresses current operational issues.