Summary

Title Related to NPRR921, RTF-2 Elimination of the Terms All-Inclusive Generation Resource and All-Inclusive Resource
Next Group
Next Step
Status Approved on 06/11/2019
Effective Dates
11/01/2019

Action

Date Gov Body Action Taken Next Steps
06/11/2019 BOARD Approved
05/22/2019 TAC Recommended for Approval Board for consideration
04/04/2019 ROS Recommended for Approval TAC for consideration
03/07/2019 ROS Recommended for Approval ROS for Impact Analysis review

Voting Record

Date Gov Body Motion Result
06/11/2019 BOARD To approve PGRR069 as recommended by TAC in the 5/22/19 TAC Report Passed
05/22/2019 TAC To recommend approval of PGRR069 as recommended by ROS in the 4/4/19 ROS Report Passed
04/04/2019 ROS To endorse and forward to TAC the 3/7/19 ROS Report and Impact Analysis for PGRR069 Passed
03/07/2019 ROS To recommend approval of PGRR069 as submitted Passed

Background

Status: Approved
Date Posted: Jan 28, 2019
Sponsor: ERCOT
Urgent: No
Sections: 5.1.1, 5.2.1, 5.2.2, 5.3.2, 5.4.2.2, 5.4.8, 5.6 (delete), 5.7.1, 5.7.3, 5.7.6, 5.7.7, 5.9, 6.8, 6.8.1, and 6.8.2
Description: This Planning Guide Revision Request (PGRR) uses the terms created in NPRR889, RTF-1 Replace Non-Modeled Generator with Settlement Only Generator, to replace the terms All-Inclusive Generation Resource and All-Inclusive Resource in the Planning Guide. Additionally, this PGRR clarifies the applicability of the Generation Interconnection or Change Request (GINR) process to different generators based on the terms created in NPRR889. Section 5.6 is deleted as it is redundant with applicable sections in the ERCOT Protocols.
Reason: Addresses current operational issues