PGRR076
Summary
Title | Improvements to Generation Resource Interconnection or Change Request (GINR) Process |
---|---|
Next Group | |
Next Step | |
Status | Approved on 08/11/2020 |
Effective Dates |
08/12/2020
All language except for paragraph (3) of Section 5.2.1 and paragraph (4)(b)(vi) of Section 5.7.1 |
Action
Date | Gov Body | Action Taken | Next Steps |
---|---|---|---|
08/11/2020 | BOARD | Approved | |
07/29/2020 | TAC | Recommended for Approval | Revision Request Consideration |
07/09/2020 | ROS | Recommended for Approval | Revision Request Consideration |
06/04/2020 | ROS | Recommended for Approval | Impact Analysis Consideration |
05/11/2020 | ROS | Recommended for Approval | Impact Analysis Consideration |
11/07/2019 | ROS | Deferred/Tabled | Language Consideration |
Voting Record
Date | Gov Body | Motion | Result |
---|---|---|---|
08/11/2020 | BOARD | to approve PGRR076 as recommended by TAC in the 7/29/20 TAC Report | Passed |
07/29/2020 | TAC | to recommend approval of PGRR076 as recommended by ROS in the 7/9/20 ROS Report, as amended by the 7/28/20 STEC comments, with an effective date of upon system implementation with a recommended priority of 2021 and rank of 3200 for paragraph (3) of Section 5.2.1 and paragraph (4)(b)(vi) of Section 5.7.1, and upon ERCOT Board approval for all remaining language. | Passed |
07/09/2020 | ROS | to endorse and forward to TAC the 6/4/20 ROS Report and the Revised Impact Analysis for PGRR076 with a recommended priority of 2021 and rank of 3200 | Passed |
06/04/2020 | ROS | to endorse the 5/11/20 ROS Report as revised by the 5/28/20 KCE comments, and that the revised Impact Analysis return to ROS | Passed |
05/11/2020 | ROS | to recommend approval of PGRR076 as amended by the 3/2/20 ERCOT comments | Passed |
11/07/2019 | ROS | to table PGRR076 and refer the issue to the Planning Working Group (PLWG) | Passed |
Background
Status: | Approved |
---|---|
Date Posted: | Oct 23, 2019 |
Sponsor: | ERCOT |
Urgent: | No |
Sections: | 5.1.1, 5.2.1, 5.4.1, 5.4.2.1, 5.4.4, 5.4.5, 5.4.8, 5.7.1, and 5.9 |
Description: | This Planning Guide Revision Request (PGRR) proposes a number of small changes to the Generation Resource Interconnection or Change Request (GINR) process as discussed at various Resource Integration Workshops. The changes include the value that must be increased to meet paragraph (1)(b)(i) of Section 5.1.1; specifying that the proposed Commercial Operations Date entered in the initial GINR application must be 15 months or greater than the date of the application; redefinition of the Security Screening Study output; creation of separate reports for the Full Interconnection Study (FIS); reactive study coordination; and clarification when the dynamic data model should be submitted to meet the quarterly stability assessment prerequisite deadlines. |
Reason: | Addresses current operational issues; Market efficiencies or enhancements |
Key Documents
Oct 23, 2019 - doc - 191 KB
Oct 23, 2019 - docx - 28.4 KB
Nov 11, 2019 - docx - 68.6 KB
Jan 3, 2020 - docx - 58.2 KB
Jan 9, 2020 - docx - 58.4 KB
Mar 2, 2020 - docx - 59.5 KB
May 14, 2020 - xls - 122.5 KB
May 14, 2020 - docx - 71 KB
May 26, 2020 - docx - 61.4 KB
May 28, 2020 - docx - 62.2 KB
Jun 9, 2020 - xls - 122 KB
Jun 9, 2020 - docx - 73.2 KB
Jul 2, 2020 - docx - 29.1 KB
Jul 7, 2020 - docx - 65.8 KB
Jul 14, 2020 - xls - 124.5 KB
Jul 14, 2020 - docx - 74.9 KB
Aug 3, 2020 - xls - 108 KB
Aug 3, 2020 - doc - 83 KB
Jul 27, 2020 - docx - 63 KB
Jul 28, 2020 - docx - 64 KB
Aug 3, 2020 - xls - 131 KB
Aug 3, 2020 - docx - 78.3 KB
Aug 14, 2020 - docx - 76.3 KB