to table PGRR089 and refer the issue to Planning Working Group (PLWG)
Passed
Background
Status:
Approved
Date Posted:
Mar 17, 2021
Sponsor:
ERCOT
Urgent:
No
Sections:
7.1
Description:
This Planning Guide Revision Request (PGRR) makes changes to the list of data sets posted to the Market Information System (MIS) in Planning Guide Section 7.1. First, it removes the Planning Horizon Transmission Capability Methodology. Second, it adds Long-Term System Assessment (LTSA) postings, Geomagnetic Disturbance (GMD) vulnerability assessments, and the monthly Generator Interconnection Status (GIS) Report to the list.
Reason:
Market efficiencies or enhancements, Administrative, Other: Retirement of NERC Reliability Standard FAC-013-2