PGRR094

Summary

Title Clarify Notification Requirement for Generator Construction Commencement or Completion
Next Group
Next Step
Status Approved on 10/28/2021

Action

Date Gov Body Action Taken Next Steps
10/28/2021 PUCT Approved
10/22/2021 BOARD Recommended for Approval Revision Request Consideration
09/29/2021 TAC Recommended for Approval Revision Request Consideration
09/02/2021 ROS Recommended for Approval Revision Request Consideration
08/05/2021 ROS Recommended for Approval Impact Analysis Consideration

Voting Record

Date Gov Body Motion Result
10/28/2021 PUCT To approve PGRR094 and accompanying ERCOT Market Impact Statement as presented in Project No. 52307, Review of Rules Adopted by the Independent Organization in Calendar Year 2021 Passed
10/22/2021 BOARD to recommend approval of PGRR094 as recommended by TAC in the 9/29/21 TAC Report Passed
09/29/2021 TAC to recommend approval of PGRR094 as recommended by ROS in the 9/2/21 ROS Report; and the Revised Impact Analysis Passed
09/02/2021 ROS to endorse and forward to TAC the 8/5/21 ROS Report and the Revised Impact Analysis for PGRR094 with a recommended priority of 2022 and rank of 3540 Passed
08/05/2021 ROS to recommend approval of PGRR094 as submitted Passed

Background

Status: Approved
Date Posted: Jul 21, 2021
Sponsor: ERCOT
Urgent: No
Sections: 5.3.2
Description: This Planning Guide Revision Request (PGRR) aligns Section 5.3.2 with current practices by greyboxing item (7)(c), which requires submission of project construction start and completion dates, until system implementation in the Resource Integration and Ongoing Operations (RIOO) – Integration Services system.
Reason: Addresses current operational issues; Administrative