MIS LOG IN

RRGRR018

Summary

Title Related to NPRR889, RTF-1 Replace Non-Modeled Generator with Settlement Only Generator
Next Group
Next Step
Status Approved on 12/11/2018

Action

Date Gov Body Action Taken Next Steps
12/11/2018 BOARD Approved
11/29/2018 TAC Recommended for Approval Board for consideration
10/11/2018 ROS Recommended for Approval TAC for consideration
09/06/2018 ROS Recommended for Approval ROS for Impact Analysis review

Voting Record

Date Gov Body Motion Result
12/11/2018 BOARD To approve RRGRR018 as recommended by TAC in the 11/29/18 TAC Report Passed
11/29/2018 TAC To recommend approval of RRGRR018 as recommended by ROS in the 10/11/18 ROS Report Passed
10/11/2018 ROS To endorse and forward to TAC the 9/6/18 ROS Report and Impact Analysis for RRGRR018 Passed
09/06/2018 ROS To recommend approval of RRGRR018 as submitted Passed

Background

Status: Approved
Date Posted: Aug 1, 2018
Sponsor: ERCOT
Urgent: No
Sections: 2
Description: This Resource Registration Glossary Revision Request (RRGRR) replaces references to Non-Modeled Generator with the new term Settlement Only Generator (SOG).
Reason: Addresses current operational issues / Market efficiencies or enhancements