MIS LOG IN

RRGRR020

Summary

Title Clarify Planning Model Requirements
Next Group
Next Step
Status Approved on 03/27/2019
Effective Dates
04/01/2019

Action

Date Gov Body Action Taken Next Steps
03/27/2019 TAC Approved
03/07/2019 ROS Recommended for Approval Revision Request Consideration
02/07/2019 ROS Recommended for Approval Impact Analysis Consideration

Voting Record

Date Gov Body Motion Result
03/27/2019 TAC to approve RRGRR020 as recommended by ROS in the 3/7/19 ROS Report Passed
03/07/2019 ROS to endorse and forward to TAC the 2/7/19 ROS Report and Impact Analysis for RRGRR020 Passed
02/07/2019 ROS to recommend approval of RRGRR020 as submitted Passed

Background

Status: Approved
Date Posted: Jan 23, 2019
Sponsor: ERCOT
Urgent: No
Sections: 2 - Skid Array Configuration Details, Panel Configuration Details, Planning
Description: This Resource Registration Glossary Revision Request (RRGRR) corrects certain submittal requirement fields inadvertently left blank during the implementation of RRGRR0007, Adding Solar Resource Registration Inputs, by replicating the requirements from the Full Interconnect Study (FIS) column to the Planning Model column for the affected rows. This RRGRR does not add any new data requirements to the Resource Registration Glossary.
Reason: Addresses current operational issues

Key Documents