MIS LOG IN

RRGRR026

Summary

Title Related to NPRR1016, Clarify Requirements for Distribution Generation Resources (DGRs) and Distribution Energy Storage Resources (DESRs)
Next Group
Next Step
Status Approved on 08/11/2020
Effective Dates
09/01/2020

Action

Date Gov Body Action Taken Next Steps
08/11/2020 BOARD Approved
07/29/2020 TAC Recommended for Approval Revision Request Consideration
07/09/2020 ROS Recommended for Approval Revision Request Consideration
06/04/2020 ROS Recommended for Approval Impact Analysis Consideration

Voting Record

Date Gov Body Motion Result
08/11/2020 BOARD to approve RRGRR026 as recommended by TAC in the 7/29/20 TAC Report Passed
07/29/2020 TAC to recommend approval of RRGRR026 as recommended by ROS in the 7/9/20 ROS Report Passed
07/09/2020 ROS to endorse and forward to TAC the 6/4/20 ROS Report and Impact Analysis for RRGRR026 Passed
06/04/2020 ROS to recommend approval of RRGRR026 as submitted Passed

Background

Status: Approved
Date Posted: Mar 25, 2020
Sponsor: ERCOT
Urgent: No
Sections: Section 2 – GENERAL_SITE_ESIID_Information - General and Site Information
Description: This Resource Registration Glossary Revision Request (RRGRR) adds a new data point to support implementation of an interim solution for representing DGRs and DESRs in the ERCOT Network Operations Model.
Reason: Addresses current operational issues; Market efficiencies or enhancements