MIS LOG IN

SMOGRR018

Summary

Title EPS Metering for Three-Wire Wye Configurations
Next Group
Next Step
Status Approved on 12/01/2016
Effective Dates
01/01/2017

Action

Date Gov Body Action Taken Next Steps
12/01/2016 TAC Approved
11/02/2016 WMS Recommended for Approval TAC for consideration
10/20/2016 MWG Recommended for Approval WMS for consideration
09/22/2016 MWG Recommended for Approval MWG for Impact Analysis review

Voting Record

Date Gov Body Motion Result
12/01/2016 TAC To approve SMOGRR018 as recommended by WMS in the 11/2/16 WMS Report Passed
11/02/2016 WMS To recommend approval of SMOGRR018 as recommended by MWG in the 10/20/16 MWG Report Passed
10/20/2016 MWG To endorse and forward to WMS the 9/22/16 MWG Report and Impact Analysis for SMOGRR018 Passed
09/22/2016 MWG To recommend approval of SMOGRR018 as submitted Passed

Background

Status: Approved
Date Posted: Aug 29, 2016
Sponsor: TIEC
Urgent: No
Sections: 1.3.2, 1.4.1
Description: This Settlement Metering Operating Guide Revision Request (SMOGRR) allows an ERCOT-Polled Settlement (EPS) Meter to be installed for a facility that is connected to a three-wire wye, high or low impedance grounded distribution system, if the high or low impedance ground is installed as part of a fault monitoring system for the facility and no phase to ground loads or phase to ground sources are connected behind the metering point.
Reason: Addresses current operational issues

Key Documents