VCMRR019

    Summary

    Title: Verifiable Cost Process Clarifications
    Next Group: TAC
    Next Step: Revision Request Consideration
    Status: Pending

    Action

    Date Gov Body Action Taken Next Steps
    09/06/2017 WMS Recommended for Approval Revision Request Consideration
    08/02/2017 WMS Recommended for Approval Impact Analysis Consideration

    Voting Record

    Date Gov Body Motion Result
    09/06/2017 WMS To endorse and forward to TAC the 8/2/17 WMS Report and Impact Analysis for VCMRR019 Passed
    08/02/2017 WMS To recommend approval of VCMRR019 as submitted. Passed

    Vote tallies here reflect individual votes, not the weight of the votes by market segment. Affirmative votes are not recorded in these vote tallies. For additional details on the voting record, please consult the Recommendation or Action Report, or the official vote tally if available, as posted in the key documents.

    Background

    Status: Pending
    Date Posted: 07/17/2017
    Sponsor: ERCOT
    Urgent: No
    Sections: 1.5, 1.6, 2.1, 2.5.1, 2.5.3, 2.6, 3.2, 3.4, 3.7, 4.1, 4.2, 4.6, 7.1.1, 9.1.3, 10.1, 10.2.1, 10.2.2, Appendix 4, Appendix 5, Appendix 6, Appendix 7, Appendix 8, Appendix 10
    Description: This Verifiable Cost Manual Revision Request (VCMRR) provides clarifications to the Verifiable Cost Manual made necessary due to the incorporation of the following Nodal Protocol Revision Requests (NPRRs) into Protocols: • NPRR485, Clarification for Fuel Adder Provisions • NPRR617, Energy Offer Flexibility • NPRR700, Utilizing Actual Fuel Costs in Startup Offer Caps ERCOT proposes one substantive change in paragraph (1) (g) of Section 10.2.1, Timeline for Verifiable Cost Submissions. The timeline for acceptance/rejection of approved Verifiable Cost has been shortened from five to three Business Days and failure to respond will result in rejection of the approved Verifiable Costs.
    Reason: Administrative

    Key Documents