Agenda
1. Antitrust Admonition
Owens
2. ROS meeting Report
Owens
3. OWG meeting minute’s approval
ALL
4. OGRRs and NOGRRs for review and language changes:
236OGRRFast Response Distributed Energy Resource (DER). This Operating Guide Revision Request (OGRR) allows for participation of Distributed Energy Resources (DERs) in Responsive Reserve Service (RRS) on an equivalent basis with synchronous condenser fast-response hydro. [Enchanted Rock]
238OGRRWGR Primary Frequency Response. The revision includes: new procedures for testing Wind-powered Generation Resource (WGR) Primary Frequency Response (new section 6.2.1.7); a new definition that applies testing of WGRs to the aggregation of all WGRs at a site; some clarifying wording for all generator’s Primary Frequency Response design requirements (2.2.5, Turbine Speed Governors); and a general change of governor to Governor in recognition of the fact that Governor is now a defined term in the protocols. [Wind Coalition]
027NOGRRRevise the Process for Submitting Biennial Unit Reactive Limits (Lead and Lag). This Nodal Operating Guide Revision Request (NOGRR) deletes Attachment E, Biennial Unit Reactive Limits (Lead and Lag) Verification in Section 8. Attachment E is no longer used as test results are submitted through the Market Information System (MIS) Certified Area. This NOGRR also updates other sections to align with the current process. [LCRA]
232OGRR Revise the Process for Submitting Biennial Unit Reactive Limits (Lead and Lag). This Operating Guide Revision Request (OGRR) deletes Section 6.2.3. The form within that Section is no longer used as results are submitted through the MIS. This OGRR also updates other sections to align with the current process. [LCRA]
032NOGRR Use of Consistent Rating Terminology. This Nodal Operating Guide Revision Request (NOGRR) proposes language changes to align rating terminology in the Nodal Operating Guides with the terminology in the Nodal Protocols. Utilization of the same verbiage helps alleviate communication issues and also removes the possible interpretation of additional rating requirements. [NDSWG]
033NOGRR Alignment with NPRR203, Amend Telemetry Bus Accuracy Requirements. This Nodal Operating Guide Revision Request (NOGRR) aligns the Nodal Operating Guides with changes proposed by Nodal Protocol Revision Request (NPRR) 203, Amend Telemetry Bus Accuracy Requirements, which clarifies the type of equipment being reported. [NDSWG]
034NOGRR Rescind Telemetry Performance Calculation Exclusions. This Nodal Operating Guide Revision Request (NOGRR) proposes the removal of language which allows Market Participants to, at their discretion, have any of their Telemetry Performance data excluded from the periodic calculations in the Telemetry Performance Monitoring Program. [ERCOT]
ALL
5. Operations Report
Monthly Operations Report Summary/Questions
Wang
6. Operations Task Force Report
Morris/Blackmer
7. Black Start Task Force Report
Kelm/Blackmer
8. Compliance Report
TRE
9. System Operations Report
Frosch/Leo
10. Other items.
PSS Clarification on definition of PSS turned on and when
Discuss PRR824 Primary Frequency Response from WGRs.
Draft NOGRR for OGRR226 under development. Possibly review of draft language.
WGR Definition - PRR 830 was approved, assignment from ROS to OWG is to review the PRR and see if any unattended consequences and review language for any impacts or operational issues
NOGRR Task Force Proposal status
Thormahlen Reid Owens
Reid/ALL
Owens
11. Adjourn
ALL
12. Future Meeting Dates: Mar 17, Apr 21, May 19, Jun 16, Jul 21, Aug 18, Sept 23, Oct 20, Nov 18, Dec 15, 2010.