TPTF Meeting |
|
February 21, 2008
09:30 AM - 05:00 PM |
RSVP:
Sheila Letkeman
|
ERCOT Austin
8000 Metropolis (Building E), Suite 100
Austin, TX 78744 Room 206A
|
Teleconference: 866-469-3239
Meeting number: 354 640 325
Meeting password: TPTF123!!
|
Agenda
Requested Links: IDA Punchlist | TPTF Punchlist | Quality Center | Nodal Metrics | Nodal Schedules | Nodal Reports | SPR 1643 Bucket |
|||
1. | Antitrust Admonition |
T. Doggett |
9:30 am |
2. | Review Agenda |
T. Doggett |
|
3. | Confirm Future TPTF Meetings:
Confirm Future Subgroup Meetings:
|
T. Doggett |
|
4. | Consider Approval of meeting minutes:
|
T. Doggett |
|
5. | Nodal Program Update / Nodal Timeline Update
|
J. Sullivan R. Chudgar |
9:40 am |
6. | TAC Update |
M. Dreyfus | 11:30 am |
7. | Readiness Metrics Inventory Maintenance
|
C. Wilkinson |
1:00 pm |
8. | Update from the February 15, 2008 Meeting of the WMS High-Low Task Force |
B. Whittle K. Ragsdale |
1:45 pm |
9. | Review of 3 Combined-Cycle potential changes | K. Ragsdale K. Hilton |
2:15 pm |
10. | COMS Update
|
B. Barnes |
2:45 pm |
11. | DAM Subgroup Issues
|
S. Siddiqi |
3:30 pm |
Recess |
End by 5:00 pm |
Scheduled TPTF Meetings
- Feb 11, 2008 - TPTF Verifiable Costs Subgroup Meeting
- Feb 12, 2008 - TPTF Subgroup: Self-Committed Resources in Day-Ahead Market
- Feb 21, 2008 - TPTF Meeting
- Feb 22, 2008 - TPTF Meeting
- Feb 25, 2008 - TPTF: Subgroup Self-Committment In DAM Meeting
- Mar 03, 2008 - TPTF Meeting
- Mar 04, 2008 - TPTF Meeting
Key Documents
07- PMO - Working Readiness Metric Inventory v0.06
(updated 02/20/08 to incorporate additional ERCOT comments)
09- COMS Details on the Settlement of Combined Cycle Plants v1.1
(revised 02/20/08)
11- Comments- MMS DAM and SASM Requirements (B2) v2.0
(DAM Subgroup)
13- Draft NPRR Step-Up Transformer Reporting Requirements
(this document merges the Luminant and Calpine comments for discussion purposes) (from the review ending Feb. 13)
13- Comments - Draft NPRR Step-Up Transformer Reporting Requirements
(Luminant, Calpine) (from the review ending Feb. 13)
14- Comments- EDS 3 LFC Testing Market Participant Handbook v1.01
(Reliant) (from the review ending Feb. 19)
14- EDS Outage Scheduler Market Participant Handbook v0.02
(blacklined version)
14- Responses- EDS Outage Scheduler Market Participant Handbook v0.01
(from the review ending Feb. 15)
14- Comments - EDS Outage Scheduler Market Participant Handbook v0.01
(AEP, CNP, LCRA, PCI, Reliant) (from the review ending Feb. 15)
14- Responses - EDS COMS Market Participant Handbook v0.01
(from the review ending Feb. 18)
14- Comments - EDS COMS Market Participant Handbook v0.01
(LCRA, The Structure Group) (from the review ending Feb. 18)
14- EDS 1 Approach v1.01
(no comments received from the review ending Feb. 14)
15- Presentation- CDR Project Schedule Status Update
(updated 02/20/08)
15- Presentation - ERCOT Extracts & Reports TPTF Review
(updated 02/21/08)
15- Comments - Section 8 Reports Spreadsheet
(Centerpoint, Luminant, TRE) (from the review ending Feb. 13)
17- Market Operations Test Environment (MOTE) Requirements (B2) v0.11
(currently in review through Feb. 26)
18- TPTF Draft Agenda Items March 3 ¿ 5, 2008
(comments due by 12pm Feb. 26)