SSWG Meeting

April 22, 2010
09:30 AM - 03:30 PM
ERCOT Austin
8000 Metropolis (Building E), Suite 100
Austin, TX 78744
Room 206A

Agenda

1

Nodal Planning Model

  1. Latest Topology Processor Output Discussion
  2. Approve SSWG System Change Request
  3. Review Progress of Corrections
  4. Review-Add to Issues List

 

 

2

Review-Update Schedule

  • April 23  ERCOT sends Pass 1 cases to SSWG
  • April 28  SSWG Conference Call
  • April 30  Pass 1 changes due to ESP
  • April 30  Complete CNG and CN updates for CRR market trials
  • May 7  ERCOT sends Pass 2 cases to SSWG (gen dispatch included)
  • May 12  SSWG Conference Call
  • May 14  Pass 2 changes due to ESP
  • May 21  ERCOT sends Pass 3 cases to SSWG
  • May 21  TSP/SSWG remaining data changes for CRR Model
  • May 26  SSWG meeting Taylor
  • May 28  ERCOT Topology Processor enhancements delivered
  • June 1  TPIT spreadsheet updates due to ERCOT
  • June to August  Make remaining changes to IMM prior to Planning Go-Live
  • June 15 to 17  SSWG meeting to finalize cases
  • June to July  TPIT update work
  • July  TSPs Complete changes
  • July  MOD/PMCR training
  • Aug  Compare TP output to SSWG 2010 summer peak case
  • Sept 1  TPIT spreadsheet updates due to ERCOT
  • Sept 21 to 23  SSWG meeting to finalize DSB cases
  • Sept to Oct  TPIT update work
  • Nov  Create 2012 summer peak case using TP and MOD
  • Dec 1  TPIT spreadsheet updates due to ERCOT
  • Dec 1  Nodal Go-Live
  • Dec to Jan 2011  TPIT update work
  • Mar to April 2011  Begin work to create 12DSA using Nodal method

 

 

 

3

11DSA

 

 

4

West Texas Wind Dispatch for cases with all CREZ facilities modeled

 

 

 

5

CPS Voltage Profile Request

 

 

6

Other Topics

 

 

 

Adjourn

 

 