OWG Meeting |
|
July 21, 2010
09:30 AM - 03:00 PM |
|
ERCOT Austin
8000 Metropolis (Building E), Suite 100
Austin, TX 78744 Room 168
|
Dial-In: 512-225-7260
Dial-In Code: 4341
|
Agenda
|
Antitrust Admonition |
Owens |
9:30 AM |
1. |
ROS meeting Report · NOGRR038, Synchronization with OGRR243, Disturbance Monitoring Requirements Clarification (Vote) approved with ERCOT comments. · Nodal Protocol/Reliability Standards Alignment Task Force (Vote) ROS approved joint task force. Check with PRS for chair and vice chair. NOGRRTF will work with this group.
|
Owens |
|
2. |
OWG meeting note’s approval |
ALL
|
|
3. |
OGRRs and NOGRRs for review and language changes: · 236OGRR Fast Response Distributed Energy Resource (DER). This Operating Guide Revision Request (OGRR) allows for participation of Distributed Energy Resources (DERs) in Responsive Reserve Service (RRS) on an equivalent basis with synchronous condenser fast-response hydro. [Enchanted Rock] Tabled until???? PRR838. · 039NOGRR Synchronization of Section 1 with Nodal Protocols. This Nodal Operating Guide Revision Request (NOGRR) aligns the Nodal Operating Guides with the Nodal Protocols by adding additional detail to Nodal Operating Guide sections that are referenced in the Nodal Protocols as well as eliminating conflicts and redundancies between the Nodal Operating Guides and Nodal Protocols. IA Review · 041NOGRR Synchronization of Section 2 with Nodal Protocols. This Nodal Operating Guide Revision Request (NOGRR) aligns the Nodal Operating Guides with the Nodal Protocols by adding additional detail to Nodal Operating Guide sections that are referenced in the Nodal Protocols as well as eliminating conflicts and redundancies between the Nodal Operating Guides and Nodal Protocols. [NOGRR TF] Language Consideration · 042NOGRR Synchronization of Section 3 with Nodal Protocols. This Nodal Operating Guide Revision Request (NOGRR) aligns the Nodal Operating Guides with the Nodal Protocols by adding additional detail to Nodal Operating Guide sections that are referenced in the Nodal Protocols as well as eliminating conflicts and redundancies between the Nodal Operating Guides and Nodal Protocols. [NOGRR TF] Language Consideration · 043NOGRR Synchronization with OGRR208, Voltage Ride-Through (VRT) Requirement. This Nodal Operating Guide Revision Request (NOGRR) relocates generator voltage requirements from Section 6, Disturbance Monitoring and System Protection, to Section 2, System Operation and Control Requirements, and establishes Voltage Ride-Through (VRT) requirements for Wind Generation Resources (WGRs) to synchronize with the zonal Operating Guides. [ERCOT] Language Consideration · 044NOGRR Clarification of a PSS In-Service. This Nodal Operating Guide Revision Request (NOGRR) clarifies that a Power System Stabilizer (PSS) must be On and in an active MW range to be considered in service. This NOGRR also updates the specific dates of PSS installation from 2008 to 2011. [LCRA] Language Consideration · 045NOGRR Synchronization of OGRR219, Time Error Correction. This Nodal Operating Guide Revision Request (NOGRR) synchronizes the Nodal Operating Guide with Operating Guide RevisionRequest (OGRR) 219, Time Error Correction, which removes the requirement that ERCOT perform time error corrections for accumulated time errors exceeding five seconds. [ERCOT] Language Consideration · 046NOGRR Synchronization of Sections 4 and 5 with Nodal Protocols. This Nodal Operating Guide Revision Request (NOGRR) aligns the Nodal Operating Guides with the Nodal Protocols by adding additional detail to Nodal Operating Guide sections that are referenced in the Nodal Protocols as well as eliminating conflicts and redundancies between the Nodal Operating Guides and Nodal Protocols. [NOGRRTF] Language Consideration · 047NOGRR Synchronization of Sections 6 and 7 with Nodal Protocols. This Nodal Operating Guide Revision Request (NOGRR) aligns the Nodal Operating Guides with the Nodal Protocols by adding additional detail to Nodal Operating Guide sections that are referenced in the Nodal Protocols as well as eliminating conflicts and redundancies between the Nodal Operating Guides and Nodal Protocols. [NOGRRTF] Language Consideration · 245OGRR Alignment with NERC Reliability Standard PRC-001-1, System Protection Coordination. This Operating Guide Revision Request (OGRR) aligns the Operating Guides with the North American Electric Reliability Corporation (NERC) Reliability Standards, specifically PRC-001-1, System Protection Requirements, Section B. Requirements, R2.2. [SPWG] Language Consideration
|
ALL
|
|
4. |
Operations Report
|
ERCOT |
|
5. |
|
Calhoun |
|
6. |
Operations Task Force Report
|
Morris/Blackmer |
|
7. |
Black Start Task Force Report
|
R. Kelm Kelly Blackmer |
|
8. |
Compliance Report
|
Texas RE |
|
9. |
System Operations
|
Frosch/Leo |
|
10. |
Other items.
a) SO-10 Voltage Management Practices Applicable to Wind Generators b) b. MD-08 Reactive and Voltage Requirements Applicable to Wind Generators c) 03._00_RWTG_Issues_List_for_ROS_and_subgroups_051310 |
Thormahlen
Reid
Group
|
|
11. |
Adjourn
|
ALL |
3:00 PM |
12. |
Future Meeting Dates: Aug 18, Sept 23, Oct 20, Nov 18, Dec 15, 2010.
|
|
|
Scheduled OWG Meetings
- Jun 16, 2010 - OWG Meeting
- Jul 07, 2010 - OGRR245 Meeting
- Jul 21, 2010 - OWG Meeting
- Aug 18, 2010 - OWG Meeting
- Sep 23, 2010 - OWG Meeting
- Oct 20, 2010 - OWG Meeting
- Nov 18, 2010 - OWG Meeting
All information is posted as Public in accordance with the ERCOT Websites Content Management Corporate Standard.