CMGRR006

Summary

Title Conforming the Competitive Metering Guide to Protocol Section 21 and Other ERCOT Market Guides
Next Group
Next Step
Status Approved on 09/06/2007

Voting Record

Date Gov Body Motion Result
09/06/2007 TAC On 09/06/07, the TAC unanimously voted to approve CMGRR006 as recommended by the RMS. All Market Segments were present for the vote. Passed
08/15/2007 RMS On 08/15/07, RMS unanimously voted to recommend approval of CMGRR006. All Market Segments were present for the vote. Passed
07/31/2007 RMWG on 7/31/07, rmwg was in consensus to forward the recommendation report and ia to the retail market subcommittee (rms) for approval. Passed

Background

Status: Approved
Date Posted: May 7, 2007
Sponsor: Sonja B. Mingo on behalf of ERCOT
Urgent: No
Sections: 17, Process for Competitive Metering Guide Revisions
Description: This Competitive Metering Guide Revision Request (CMGRR) conforms the revision process for the Competitive Metering Guide (CMG) to Protocol Section 21 and other ERCOT market guides by : Updating the CMG to accurately reflect NERC name change. Requiring that a CMGRR associated with and ERCOT project be assigned to the œUnfunded Project Lis€? unless the project can be funded in the current ERCOT budget cycle based upon its priority and ranking; Providing specific guidelines for RMS to use when determining whether a CMGRR should be considered urgent; andProposing non-substantive changes for formatting, stylistic, and administrative change
Reason: Conformance to the current ERCOT Protocols and other ERCOT market guides.

Key Documents