to approve COPMGRR049 and accompanying ERCOT Market Impact Statement as presented in Project No. 54445, Review of Rules Adopted by the Independent Organization
to grant COPMGRR049 Urgent status; to recommend approval of COPMGRR049 as revised by WMS; and to forward to TAC COPMGRR049 and the 2/22/23 Impact Analysis
Passed
Background
Status:
Approved
Date Posted:
Feb 22, 2023
Sponsor:
ERCOT
Urgent:
Yes
Sections:
4.1, 4.3.2, 4.3.3, 4.3.9, 4.3.10, 4.3.11 (new), 4.4, and 4.6
Description:
This Commercial Operations Market Guide Revision Request (COPMGRR) requires all Revision Requests to be approved by the Public Utility Commission of Texas (PUCT) prior to implementation; standardizes all Revision Requests be considered by the ERCOT Board of Directors; adds an Independent Market Monitor (IMM) opinion, ERCOT opinion, and the ERCOT Market Impact Statement to the TAC Report; and revises possible actions on a Revision Request from “defer” to “table” as currently captured in motions.