To grant Urgent status for, LPGRR031, Profile Decision Tree Changes for Distributed Renewable Generation
Passed
Background
Status:
Approved
Date Posted:
Sep 8, 2008
Sponsor:
Ernie Podraza on behalf of the Profiling Working Group (PWG)
Urgent:
Yes
Sections:
Appendix D: Profile Decision Tree
Description:
This LPGRR removes IDRRG as a Profile Segment, specifies information requirements based on Distributed Renewable Generation (DRG) capacity and includes mapping of new zip codes to Weather Zones.
Reason:
To remove IDRRG as a valid Profile Segment because it is addressed by other Profile Segments, specify assignment of BUSIDRRQ should not be changed if the Electric Service Identifier (ESI ID) has DRG, lessen the amount of information Transmission and/or Distribution Service Providers (TDSPs) need to provide ERCOT from interconnection agreement and provide mapping of additional zip codes to Weather Zones.