MIS LOG IN

NOGRR026

Summary

Title Change the name of Emergency Electric Curtailment Plan (EECP) to Energy Emergency Alert (EEA) and Synchronization of EEA Steps with Protocols
Next Group
Next Step
Status Approved on 11/05/2009
Effective Dates
12/01/2010

or per the Nodal Protocol Transition Plan http://www.ercot.com/mktrules/protocols (12/01/09 Nodal Operating Guide Library)

Action

Date Gov Body Action Taken Next Steps
11/05/2009 TAC Approved
10/15/2009 ROS Recommended for Approval TAC Consideration
09/15/2009 OWG Recommended for Approval ROS consideration
08/19/2009 OWG Recommended for Approval OWG consider the Recommendation Report and IA.

Voting Record

Date Gov Body Motion Result
11/05/2009 TAC To approve NOGRR026 as recommended by ROS in the 10/15/09 ROS Recommendation Report. Passed
10/15/2009 ROS To recommend approval of NOGRR026 as recommended by OWG in the 9/15/09 OWG Recommendation Report. Passed
09/15/2009 OWG On 9/15/09, OWG was in consensus to endorse and forward the 8/19/09 OWG Recommendation Report and Impact Analysis for NOGRR026 to ROS. Passed
08/19/2009 OWG Consensus to recommend approval of NOGRR026 as submitted. Passed

Background

Status: Approved
Date Posted: Jul 13, 2009
Sponsor: Colleen Frosch
Urgent: No
Sections: 1.4, Definitions 2.2.1, Overview 2.2.9.2, Time Synchronization 2.3, Ancillary Services 2.6.1, Automatic Firm Load Shedding 4.1, Introduction 4.2.3, Alert 4.4, Block Load Transfers between ERCOT and Non-ERCOT System 4.5, Emergency Electric Curtailment Plan (EECP) 4.5.1, General 4.5.3, Implementation 4.5.3.1, General Procedures Prior to EECP Operations 4.5.3.2, General Procedures During EECP Operations 4.5.3.3, EECP Steps 4.5.3.5, EECP Termination
Description: This Nodal Operating Guide Revision Request (NOGRR) changes the name of the Emergency Electric Curtailment Plan (EECP) to Energy Emergency Alert (EEA), the defined term "Alert" to "Watch", and replaces "BtB" with "DC-Tie". This NOGRR also aligns the EEA Steps in the Nodal Operating Guides with the Nodal Protocols. The NOGRR deletes the definition of "Physical Responsive Capability (PRC)" since this term is already defined in the Nodal Protocols.
Reason: Aligns the Nodal Operating Guides with the Nodal Protocols. This NOGRR changes Nodal Operating Guide language only and not procedure.

Key Documents