NOGRR027
Summary
Title | Revise the Process for Submitting Biennial Unit Reactive Limits (Lead and Lag) |
---|---|
Next Group | |
Next Step | |
Status | Approved on 04/08/2010 |
Effective Dates |
12/01/2010
or per the Nodal Protocol Transition Plan http://www.ercot.com/mktrules/protocols (05/01/10 Nodal Operating Guide Library) |
Action
Date | Gov Body | Action Taken | Next Steps |
---|---|---|---|
04/08/2010 | TAC | Approved | |
03/11/2010 | ROS | Recommended for Approval | TAC for consideration |
02/19/2010 | OWG | Recommended for Approval | ROS Consideration |
01/18/2010 | OWG | Recommended for Approval | OWG IA Review |
12/16/2009 | OWG | Deferred/Tabled | OWG Review |
11/17/2009 | OWG | Deferred/Tabled | OWG Review |
10/21/2009 | OWG | Deferred/Tabled | OWG Review |
09/15/2009 | OWG | Deferred/Tabled | OWG Consideration |
08/19/2009 | OWG | Recommended for Approval | OWG IA Review |
Voting Record
Date | Gov Body | Motion | Result |
---|---|---|---|
04/08/2010 | TAC | To approve NOGRR027 as recommended by ROS in the 3/11/10 ROS Recommendation Report | Passed |
03/11/2010 | ROS | To recommend approval of NOGRR027 as recommended by OWG in the 2/19/10 OWG Recommendation Report and as revised by ROS. | Passed |
02/19/2010 | OWG | Consensus to endorse and forward the 1/18/10 OWG Recommendation Report and Impact Analysis for NOGRR027 to ROS | |
01/18/2010 | OWG | Consensus to recommend approval of NOGRR027 as revised by OWG | |
12/16/2009 | OWG | Consensus to table NOGRR027 for one month | |
11/17/2009 | OWG | Consensus to table NOGRR027 for one month | |
10/21/2009 | OWG | Consensus to table for one month. | |
09/15/2009 | OWG | Consensus to table NOGRR027 for one month. | |
08/19/2009 | OWG | Consensus to recommend approval of NOGRR027 as revised by OWG |
Background
Status: | Approved |
---|---|
Date Posted: | Jul 17, 2009 |
Sponsor: | LCRA |
Urgent: | No |
Sections: | 3.3.2.1, 3.3.2.2, 3.3.2.3, Section 8 - Attachment E |
Description: | This Nodal Operating Guide Revision Request (NOGRR) deletes Attachment E, Biennial Unit Reactive Limits (Lead and Lag) Verification in Section 8. Attachment E is no longer used as test results are submitted through the Market Information System (MIS) Certified Area. This NOGRR also updates other sections to align with the current process. |
Reason: | Attachment E in Section 8 has been superseded by the ERCOT requirement to submit all biennial unit reactive limit tests through the MIS Certified Area. The process for submitting test results through the MIS Certified Area is similar but requires more data than the current form. The circulation of VARs allows the unit to accomplish a lagging reactive test with minimal constraints from the transmission system. |
Key Documents
Jul 17, 2009 - doc - 109 KB
Jul 17, 2009 - doc - 156 KB
Aug 25, 2009 - doc - 110.5 KB
Sep 8, 2009 - doc - 45.5 KB
Sep 16, 2009 - doc - 110.5 KB
Oct 20, 2009 - doc - 77.5 KB
Oct 23, 2009 - doc - 111.5 KB
Nov 19, 2009 - doc - 112 KB
Dec 19, 2009 - doc - 112.5 KB
Jan 20, 2010 - doc - 117 KB
Feb 22, 2010 - doc - 118 KB
Mar 15, 2010 - doc - 121 KB
Apr 12, 2010 - doc - 122.5 KB