NOGRR034

Summary

Title Rescind Telemetry Performance Calculation Exclusions
Next Group
Next Step
Status Approved on 09/21/2010
Effective Dates
12/01/2010

or per the Nodal Protocol Transition Plan http://www.ercot.com/mktrules/protocols (10/01/10 Nodal Operating Guide Library)

Action

Date Gov Body Action Taken Next Steps
09/21/2010 BOARD Approved
08/05/2010 TAC Recommended for Approval ERCOT Board consideration.
07/22/2010 PRS Recommended for Approval TAC for consideration.
07/15/2010 ROS Recommended for Approval PRS for consideration.
06/10/2010 ROS Recommended for Approval ROS for consideration.
05/19/2010 OWG Recommended for Approval ROS for consideration.
04/21/2010 OWG Recommended for Approval OWG for review of Impact Analysis
03/17/2010 OWG Deferred/Tabled OWG for language consideration.
02/19/2010 OWG Deferred/Tabled OWG for language consideration.

Voting Record

Date Gov Body Motion Result
09/21/2010 BOARD To approve NOGRR034 as recommended by TAC in the 8/5/10 TAC Report. Passed
08/05/2010 TAC To recommend approval of NOGRR034 as recommended by ROS in the 7/15/10 ROS Recommendation Report. Passed
07/22/2010 PRS To recommend a priority of Medium for the proposed grey-box language in NOGRR034. Passed
07/15/2010 ROS To recommend a priority of Medium for the proposed grey-box language in NOGRR034. Passed
06/10/2010 ROS To recommend approval of NOGRR034 as amended by the 6/3/10 ERCOT comments. Passed
05/19/2010 OWG Consensus to endorse and forward the 4/21/10 OWG Recommendation Report for NOGRR034 as revised by OWG to ROS and to request that a revised Impact Analysis be forwarded directly to ROS for consideration.
04/21/2010 OWG To recommend approval of NOGRR034 as revised by OWG.
03/17/2010 OWG Consensus to table NOGRR034 for one month to allow ERCOT and NDSWG to agree on language.
02/19/2010 OWG To table NOGRR034 for one month to allow the Network Data Support Working Group (NDSWG) to comment.

Background

Status: Approved
Date Posted: Jan 22, 2010
Sponsor: ERCOT
Urgent: No
Sections: 7.3.3
Description: This Nodal Operating Guide Revision Request (NOGRR) proposes the removal of language which allows Market Participants to, at their discretion, have any of their Telemetry Performance data excluded from the periodic calculations in the Telemetry Performance Monitoring Program.
Reason: There is no project in scope or budget to account for these exclusions and adjust the calculations in the Telemetry Performance monitoring program.