NOGRR076

Summary

Title Synchronization with NPRR298 and New Format for Black Start Plans
Next Group
Next Step
Status Approved on 10/06/2011
Effective Dates
12/14/2011

Action

Date Gov Body Action Taken Next Steps
10/06/2011 TAC Approved
09/15/2011 ROS Recommended for Approval TAC Consideration
08/17/2011 OWG Recommended for Approval ROS Consideration
07/20/2011 OWG Recommended for Approval OWG IA Review

Voting Record

Date Gov Body Motion Result
10/06/2011 TAC To approve NOGRR076 as recommended by ROS in the 9/15/11 ROS Report and as amended by the 10/5/11 ERCOT comments Passed
09/15/2011 ROS To recommend approval of NOGRR076 as amended by the 9/15/11 BSWG comments and as revised by ROS with an effective date of "upon TAC approval Passed
08/17/2011 OWG Consensus to endorse and forward the 7/20/11 OWG Report as revised by OWG and Impact Analysis for NOGRR076 to ROS
07/20/2011 OWG Consensus to recommend approval of NOGRR076 as revised by OWG

Background

Status: Approved
Date Posted: Jul 5, 2011
Sponsor: Black Start Working Group (BSWG)
Urgent: No
Sections: 1.4, 1.5.1, 2.3, 4.3, 4.5.2, 4.6, 4.6.1, 4.6.2, 4.6.3, 4.6.4, 4.6.5, 8A, 8E (new)
Description: This Nodal Operating Guide Revision Request (NOGRR): · Synchronizes the Nodal Operating Guides with Nodal Protocol Revision Request (NPRR) 298, New Definitions Related to Black Start and Clarification to the Hourly Standby Fee Payments for Black Start Resources (formerly "New Definitions Related to Black Start"), which introduced new black start terminology and corrected the acronym related to the Hourly Standby Fee Payment. NPRR298 was approved by the ERCOT Board on April 19, 2011. · Introduces new black start terminology to the Nodal Operating Guides; · Creates a requirement for all Transmission Operators (TOs) to submit their Black Start Plans to ERCOT by November 1 of each year; andIntroduces a template for Black Start Plans to the Nodal Operating Guides.
Reason: This NOGRR synchronize the Nodal Operating Guides with NPRR298 and clarifies the processes and terminology currently used for restoration of the ERCOT System. Additionally, a Black Start Plan template is necessary so that all TOs provide the information necessary for ERCOT to develop its Black Start Plan.