To endorse and forward the 12/6/12 ROS Report as amended by the 1/14/13 ERCOT comments and as revised by PRS and the Impact analysis for NOGRR101 to TAC with a recommended priority of 2013 and rank of 815
To recommend approval of NOGRR101 as amended by the 10/22/12 Tenaska Power Services Co. comments and as revised by ROS with a recommended priority of 2013 and rank of 815
Consensus to recommend approval of NOGRR101 as revised by the 8/13/12 ERCOT comments
Background
Status:
Approved
Date Posted:
Jul 26, 2012
Sponsor:
Tenaska Power Services Co.
Urgent:
No
Sections:
10 (new), 10.1 (new)
Description:
This Nodal Operating Guide Revision Request (NOGRR) provides that ERCOT shall produce a detailed report regarding any outage of a Direct Current Tie (DC Tie) in a timely manner.
Reason:
Outages of interconnection points between the ERCOT and non-ERCOT Control Areas have market implications on both the ERCOT market and the interconnected market. Detailed information regarding such outages is necessary for Market Participants on both sides of the interconnection point to be able to manage risk associated with such outages.