Consensus to endorse and forward the 7/17/13 OWG Report, as amended by the 9/17/13 ERCOT comments and as revised by OWG, and the Impact Analysis for NOGRR111 to ROS.
This Nodal Operating Guide Revision Request (NOGRR) synchronizes the Nodal Operating Guide with NPRR527, Required Combined Cycle Telemetry for Operational Awareness and PDCWG Analysis, requires Combined Cycle Generation Resources to telemeter individual High Sustainable Limits (HSLs) for gas and steam turbines. The HSLs for combustion and steam turbines were previously submitted in zonal and ERCOT requests this practice be resumed in the nodal.
Reason:
Removes the requirement for the submission of limits due to the additional telemetry which will be provided by Combined Cycle Generation Resources via NPRR527.