NOGRR118

Summary

Title Hydro Responsive Test Reporting
Next Group
Next Step
Status Approved on 09/05/2013
Effective Dates
10/01/2013

Action

Date Gov Body Action Taken Next Steps
09/05/2013 TAC Approved
08/15/2013 ROS Recommended for Approval TAC for consideration
07/17/2013 OWG Recommended for Approval ROS for consideration
06/19/2013 OWG Recommended for Approval OWG IA Review

Voting Record

Date Gov Body Motion Result
09/05/2013 TAC To approve NOGRR118 as recommended by ROS in the 8/15/13 ROS Report. Passed
08/15/2013 ROS To recommend approval of NOGRR118 as recommended by OWG in the 6/19/13 OWG Report. Passed
07/17/2013 OWG Consensus to endorse and forward the 6/19/13 OWG Report and Impact Analysis for NOGRR118 to ROS. Passed
06/19/2013 OWG Consensus to recommend approval of NOGRR118 as submitted. Passed

Background

Status: Approved
Date Posted: Jun 3, 2013
Sponsor: ERCOT
Urgent: No
Sections: 9.4.1
Description: This Nodal Operating Guide Revision Request (NOGRR) revises the requirement for ERCOT to develop a monthly report related to hydro responsive tests to a quarterly report.
Reason: Paragraph (6) of Protocol Section 8.1.1.2, General Capacity Testing Requirements, requires Resources providing hydro Responsive Reserve Service (RRS) to evaluate capability each Season.

Key Documents