To recommend approval of NOGRR124 as recommended by OWG in the 3/19/14 OWG Report, but notes that ROS expresses disappointment with the retroactivity of NOGRR124.
To recommend approval of NOGRR124 as amended by 2/12/14 EDF-RE comments and as revised by OWG, with the exception of endorsing any particular grandfathering date.
This Nodal Operating Guide Revision Request (NOGRR) specifies new high Voltage Ride-Through (VRT) requirements for Intermittent Renewable Resources (IRRs) and prohibits IRRs from tripping for events that are less severe than the defined thresholds and occur for shorter time durations.
Reason:
To maintain system reliability by establishing additional VRT requirements for IRRs.