NOGRR129
Summary
Title
Implement Operational Preparedness for Geomagnetic Disturbances
Next Group
Next Step
Status
Approved on 06/26/2014
Effective Dates
Voting Record
Date
Gov Body
Motion
Result
06/26/2014
TAC
To approve as recommended by ROS in the 6/5/14 ROS Report and as revised by TAC
Passed
06/05/2014
ROS
To recommend approval of NOGRR129 as recommended by OWG in the 5/19/14 OWG Report
Passed
05/19/2014
OWG
To endorse and forward the 4/23/14 OWG Report and Impact Analysis to ROS
Passed
04/23/2014
OWG
To recommend approval of NOGRR129 as amended by the 4/22/14 ERCOT comments.
Passed
Background
Status:
Approved
Date Posted:
Mar 12, 2014
Sponsor:
GMDTF
Urgent:
No
Sections:
1.4, 4.7 (new), 4.7.1 (new), 4.7.2 (new), 4.7.3 (new)
Description:
This Nodal Operating Guide Revision Request (NOGRR) sets up an ERCOT Region coordination process through which ERCOT and Transmission Operators (TOs) will develop Geomagnetic Disturbance (GMD) operating documents and communicates such information.
Reason:
To meet regulatory requirements