Title | Alignment with NPRR705, Provides Consistency for References to the End Date of the Generation Interconnection Process |
---|---|
Next Group | |
Next Step | |
Status | Approved on 12/16/2015 |
Effective Dates |
01/01/2016
|
Action
Date | Gov Body | Action Taken | Next Steps |
---|---|---|---|
12/16/2015 | TAC | Approved | |
10/29/2015 | TAC | Deferred/Tabled | Revision Request Consideration |
10/08/2015 | ROS | Recommended for Approval | Revision Request Consideration |
09/17/2015 | OWG | Recommended for Approval | Revision Request Consideration |
08/20/2015 | OWG | Recommended for Approval | Impact Analysis Consideration |
07/23/2015 | OWG | Deferred/Tabled | Language Consideration |
06/18/2015 | OWG | Deferred/Tabled | Language Consideration |
Voting Record
Date | Gov Body | Motion | Result |
---|---|---|---|
12/16/2015 | TAC | To approve NOGRR145 as recommended by ROS in the 10/8/15 ROS Report. | Passed |
10/29/2015 | TAC | To table NOGRR145. | Passed |
10/08/2015 | ROS | To recommend approval of NOGRR145 as recommended by OWG in the 9/17/15 OWG Report. | Passed |
09/17/2015 | OWG | To endorse and forward to ROS the 8/20/15 OWG Report and Impact Analysis for NOGRR145. | Passed |
08/20/2015 | OWG | To recommend approval of NOGRR145 as submitted. | Passed |
07/23/2015 | OWG | To table NOGRR145. | Passed |
06/18/2015 | OWG | To table NOGRR145 for one month. | Passed |
Background
Status: | Approved |
---|---|
Date Posted: | May 20, 2015 |
Sponsor: | ERCOT |
Urgent: | No |
Sections: | 2.2.6 |
Description: | In the Resource Interconnection Handbook, the term “commercial operations” has a different meaning to Resource Entities and financial institutions involved in construction and financing of Generation Resources than it does in the context of performance testing by ERCOT for new Generation Resources. This Nodal Operating Guide Revision Request (NOGRR) aligns the Nodal Operating Guides with NPRR705 by replacing various terms used to refer to the date on which Generation Resources complete the Resource interconnection process with the proposed defined terms “Commercial Operations Date” and “Resource Commissioning Date” to provide consistency for references to the end of the generation interconnection process. |
Reason: | Administrative |
Key Documents
May 20, 2015 - doc - 55.5 KB
Jun 19, 2015 - doc - 85.5 KB
Jul 27, 2015 - doc - 86.5 KB
Aug 21, 2015 - doc - 83.5 KB
Sep 21, 2015 - doc - 84 KB
Oct 12, 2015 - doc - 90 KB
Oct 30, 2015 - doc - 87.5 KB
Nov 11, 2015 - doc - 55.5 KB
Dec 17, 2015 - xls - 106 KB
Dec 17, 2015 - doc - 87 KB