NOGRR147
Summary
Title
Reactive Power Testing Requirements
Next Group
Next Step
Status
Approved on 02/09/2016
Effective Dates
Voting Record
Date
Gov Body
Motion
Result
02/09/2016
BOARD
To approve NOGRR147 as recommended by TAC in the 1/28/16 TAC Report
Passed
01/28/2016
TAC
To recommend approval of NOGRR147 as recommended by ROS in the 12/8/15 ROS Report.
Passed
12/08/2015
ROS
Voted via email vote to recommend approval of NOGRR147 as recommended by OWG in the 11/17/15 OWG Report.
Passed
11/17/2015
OWG
To endorse and forward to ROS the 10/22/15 OWG Report and the Impact Analysis for NOGRR147 with a recommended priority of 2016 and rank of 1530.
Passed
10/22/2015
OWG
To table NOGRR147.
Passed
09/17/2015
OWG
To recommend approval of NOGRR147 as amended by the 9/8/15 Reactive Power Testing Requirements Workshop comments.
Passed
07/23/2015
OWG
To table NOGRR147.
Passed
Background
Status:
Approved
Date Posted:
Jun 29, 2015
Sponsor:
Luminant
Urgent:
No
Sections:
3.3.2.1, 3.3.2.2, 3.3.2.3, 3.5
Description:
This Nodal Operating Guide Revision Request (NOGRR) revises the language in Section 3.3.2.1, Corrected Unit Reactive Limits (CURL), to harmonize the ERCOT reactive testing requirements with the recently approved North American Electric Reliability Corporation (NERC) Reliability Standards.
Reason:
Regulatory requirements